Choose the trigger first
Write observable conditions that stop the move: failed core forms, an invalid certificate, missing current orders, or an unavailable critical integration. Separate these from low-impact cosmetic defects. Name the person who can call rollback and the person who will execute it. Avoid a plan where everyone assumes someone else decides.
Read the example
The tool example allows 40 minutes for final copy, 20 for checks, 30 for observation and 30 for rollback. The total is 120 minutes. Against a 150-minute window, 30 minutes remain unallocated. That arithmetic is a planning allowance, not a measured recovery time. Replace each estimate with evidence from a rehearsal.
Account for writes
If visitors can create orders or change records after cutover, sending them back to an old database may lose or duplicate activity. Document how writes are paused, reconciled or replayed. A DNS reversal does not reverse database changes. If the data cannot safely move backward, the recovery plan may need a repair-forward procedure instead.
Close the window deliberately
Record the last safe decision point, the actual decision time and the post-rollback checks. Keep both environments available until the agreed observation period ends. After a successful migration, restore ordinary cache settings where appropriate, archive the runbook and retire old access through the normal process. Do not delete the old environment just because the first homepage request succeeded.